The project successfully completed the full validation process of the integration of the Nabrajoint solution into wind turbine blade from a leading OEM (client undisclosed).
Based on M33-certified Nabrajoint elements, the project included the following key phases:

  • Joint adaptation: engineering the solution to meet client’s specific load conditions, blade geometry and manufacturing process, and logistical constraints.
  • Custom slab manufacturing: production of Nabrajoint parts tailored to the client’s blade shell.
  • Split blade manufacturing: successful integration of the Nabrajoint slabs into the client’s blade manufacturing process.
  • Full-scale blade testing: comprehensive testing of blade and joint confirmed full structural compliance.

The project demonstrated the feasibility of implementing Nabrajoint technology in blades longer than 80 meters, for > 6 MW wind turbines, enabling the use of split blades for logistically constrained onshore markets.